Villas at Hamilton
Progress Photos for week ending October 24, 2002

   

Bldg 422 Fire line being installed


Bldg 422 Elevator being installed.


Bldg 422 Forming front Main Entry steps


Bldg 422 Spreading glue for carpets


Bldg 422 Cabinets ready for counters and appliances


Bldg 420 Window sills being installed


Bldg 420 Rooms ready for paint


Bldg 420 Carpenters building window sills


Bldg 420 Hallways getting ready for paint


Bldg 424 Sprinklers being installed


Bldg 424 Sprinklers being pressure tested


Bldg 424 Unit rough-in nearly complete


Bldg 424 Hallway rough-in complete


Bldg 424 Metal studs ready for sheetrock


Bldg 424 Veranda walls ready for stucco