Construction process
- Step 1 – Design and layout
- Step 2 – Permits and HOA approval if necessary
- Step 3 – Excavation
- Step 4 – Steel (Installation of rebar before application of gunite)
- Step 5 – Underground plumbing, gas lines and electrical conduit
- Step 6 – Inspection by local authorities
- Step 7 – Application of gunite
- Step 8 – Backfill and grade for decking
- Step 9 – Set up forms for concrete decking
- Step 10 – Inspection by local authorities
- Step 11 – Pour concrete decking
- Step 12 – Installation of waterline tile and/or stone
- Step 13 – Install filtration equipment
- Step 14 – Inspection by local authorities
- Step 15 – Apply plaster or pebble finish to pool
- Step 16 – Start up (varies depending on finish)
- Step 17 – Final inspection by local authorities
- Step 18 – Homeowner walk-through to ensure complete satifaction
- Step 19 – ENJOY!
|