Using the Canon Digital Elph and taking three differently-sited images each day the construction crew were working, this is a 75-day time-lapse movie of the house modifications and additions. No images were taken on days when the crew was not working and some work occured out of view of the camera, such as the plumbing, HVAC, electrical and drywall. Most times the construction crew had something to do outside while subcontractors worked inside, but in the latter stages there are a few days where there is no visible change to the outside. Direct link to movie file is http://homepage.mac.com/credmond/WatchHouseWork.mov. Real work began on March 31st and the last work was done on July 29th.
|